loading


Wedone Group offers turnkey hot-dip galvanizing plants and automated solutions

How To Plan Utility Capacities Power Gas Water And Compressed Air For A New Hot-Dip Galvanizing Plant

The operational success of a hot-dip galvanizing facility depends fundamentally on the robustness and foresight of its utility infrastructure planning. Electrical power, natural gas, process water, cooling water, and compressed air form the operational backbone of any galvanizing operation. The manner in which these utilities are sized, integrated, and designed for future scalability determines whether a facility achieves operational excellence or contends with chronic bottlenecks, unplanned downtime, and costly retrofits.

This guide provides engineering professionals and project managers with practical, actionable frameworks for planning utility capacity in hot-dip galvanizing plants. Drawing upon industry standardsincluding NFPA 86, IEEE 519, ISO 8573, and ASME B31.3as well as engineering best practices and operational lessons learned, we examine each utility in depth, illuminate common design pitfalls, and present strategies for building resilient, scalable infrastructure capable of adapting to evolving production demands.


The Strategic Importance of Early Utility Planning

Utility planning is not a design-phase checkbox; it is a strategic activity that directly impacts production stability, capital allocation, and long-term operational efficiency. Industry experience consistently demonstrates that under-sized utilities rank among the most frequent causes of production interruptions in newly commissioned galvanizing plants. Conversely, over-specified systems waste capital and erode operational efficiency through poor part-load performance.


1 Consequences of Under-Sizing

Under-sized utility systems manifest in multiple detrimental ways:


  • Production interruptions: Voltage sags, gas pressure drops, cooling water temperature excursions, and compressed air starvation can halt production lines with little warning.
  • Equipment damage: Motors operating at reduced voltage overheat; compressors short-cycling suffer accelerated wear; transformer overload accelerates insulation aging.
  • Zinc solidification risk: A critical risk in galvanizing operations is zinc solidification in the kettle during extended power outages. Recovery can require days of reheating, with substantial material and productivity losses. This single failure mode justifies careful attention to backup power design regardless of perceived grid reliability.

2 The Cost of Over-Sizing

Conversely, over-specified utilities create their own challenges: unnecessarily high capital expenditure, elevated standing operating costs, reduced equipment efficiency at partial load, and increased maintenance burdens. Equipment operating well below design capacity suffers from:

  • Short-cycling: Frequent on/off operation accelerates wear and reduces efficiency.
  • Reduced loading: Motors and compressors operate in inefficient zones of their performance curves.
  • Higher standing losses: Transformers, pumps, and fans consume energy regardless of production level.

The optimal approach matches utility capacity to validated operational requirements while incorporating rational safety marginstypically 1015% for most systems, with higher margins only where justified by specific process risks or growth plans.


3 Early Engagement with Utility Providers

Utility providers in many regions face multi-year lead times for infrastructure upgrades. Grid connection capacity, natural gas pipeline extensions, and water supply augmentation often require formal applications, environmental assessments, and capital approval cycles. Engaging providers at the conceptual design stageideally 1824 months before planned commissioningis essential to:


  • Validate available supply capacity at the proposed site.
  • Establish realistic connection timelines.
  • Negotiate demand charges and tariff structures.
  • Identify infrastructure upgrade requirements and associated costs.
  • Clarify regulatory and environmental compliance expectations.
  • Understand curtailment procedures and interruption histories.
  • Confirm voltage, pressure, and flow quality parameters at point of common coupling.

Electrical Power Systems

1 Assessing Power Demand

The galvanizing furnace typically represents the largest single electrical load in the facility. However, a complete power assessment must consider all electrical consumers, including:

Primary Process Loads- Furnace heating elements (resistance) or induction coils.
- Preheat furnaces and drying ovens.
- Zinc kettle auxiliary heating systems.

Material Handling Systems- Overhead cranes and hoists.
- Conveyor drives and indexing systems.
- Robotic or automated dipping systems.

Support Systems- Air compressors.
- Cooling water pumps and cooling tower fans.
- Hydraulic power units for press and forming equipment.
- Exhaust and ventilation fans.

Controls and Instrumentation- PLC systems, HMIs, and control panels.
- Process analyzers and sensors.
- Safety systems and alarms.
- Lighting and HVAC systems.

Practical note on documentation: Create a comprehensive load inventory spreadsheet from day one, listing each consumer with its nameplate rating, operating voltage, duty cycle, load factor, and diversity factor. This document becomes the foundation for all subsequent design decisions and is essential for verifying assumptions during commissioning.


2 Demand Profile Analysis

A rigorous demand assessment distinguishes between:

  • Average Load: The typical power draw during normal production. This value underpins energy consumption forecasting and utility cost estimation.
  • Peak Demand: The maximum instantaneous power draw, typically occurring during:
  • Furnace cold-start and heat-up cycles.
  • Simultaneous operation of multiple production lines.
  • Heavy production campaigns with large-volume or complex-geometry parts.
  • Coincident startup of large motors (cranes, compressors, pumps).

Calculation Methodology:

$$\text{Total Average Demand} = \sum (\text{Individual Load} \times \text{Duty Cycle} \times \text{Load Factor})$$

$$\text{Peak Demand} = \sum (\text{Individual Load} \times \text{Load Factor} \times \text{Coincidence Factor})$$

The coincidence factor (typically 0.70.9 for galvanizing plants) accounts for the operational reality that not all equipment operates at full load simultaneously. When actual duty cycles are unknown during design, consult equipment manufacturers and reference data from existing comparable installations. A conservative initial estimate using a coincidence factor of 0.85 is recommended for preliminary sizing, refined as operational data become available.


3 Transformer and Switchgear Sizing

A common engineering error is sizing transformers based on average load rather than peak demand. This creates avoidable failures:

  • Voltage sag during high-production periods, causing motor overheating and process control instability.
  • Transformer overload accelerating insulation aging and reducing service life.
  • Protective device nuisance tripping interrupting otherwise healthy operations.

Sizing Guidelines

  • Size transformers to handle peak demand plus the design safety margin. Industry practice varies by region: IEEE guidance typically supports margins of 115125% of calculated peak in North America, while IEC practice often adopts 110120% with explicit consideration of loading cycles per IEC 60076-7.
  • Factor in future expansion allowance where plant growth is anticipated.
  • Specify transformers with appropriate kVA ratings and impedance characteristics to limit fault levels within switchgear ratings.
  • Select conservatively for ambient temperature conditions and installation location (indoor/outdoor).

Voltage Selection

Most galvanizing plants operate on medium-voltage distribution (e.g., 11 kV or 13.8 kV primary, stepped down to 480 V or 400 V secondary). Consider:


  • Furnace power supplies may require dedicated transformers to isolate harmonic loads.
  • Variable frequency drives (VFDs) may require line reactors or active harmonic filters.
  • Large induction heating loads may benefit from higher distribution voltages.
  • The criticality of supplying large motor loads at voltages that minimize inrush current impacts.

4 Backup Power Systems

The production downtime risk in a galvanizing plant is acute. Zinc solidifying in the kettle during a prolonged outage can require days of reheating to recover, with substantial material and productivity losses. Backup power design must therefore prioritize kettle thermal integrity above all other loads.

Critical Loads Requiring Backup Power

  • Furnace control and temperature monitoring systems.
  • Kettle heating elements (at least partial capacity to maintain zinc above solidification temperaturetypically 420C for pure zinc; the required heating power depends on kettle thermal mass and insulation losses).
  • Safety interlock systems and emergency alarms.
  • Emergency lighting and egress systems.
  • Minimum process lighting for inspection and evacuation.

Backup Options

  1. Uninterruptible Power Supply (UPS): Covers instantaneous transitions and protects sensitive electronics. Sized for controls, instrumentation, and safety systems, typically for 1560 minutes of ride-through.
  2. Diesel generator set: Sized at 3050% of peak demand to support critical process loads during extended outages. For kettle heating specifically, generator capacity should be sufficient to maintain zinc temperature (not necessarily to melt solid zinc). This typically requires 2040% of the furnace's rated heating capacity, depending on kettle insulation and ambient conditions.
  3. Battery energy storage systems (BESS): Emerging as a viable option for bridging short outages and demand peak shaving, with response times faster than generator start-up.
  4. Dual utility feeds: Where available from independent substations, dual feeds provide inherent redundancy worth evaluating against the cost of on-site generation.

Design Recommendation: A layered approach is best. UPS systems cover instantaneous transitions and protect sensitive electronics, while a diesel generator set supports critical process loads during extended outages. Configure automatic transfer switches to sequence load restoration and avoid simultaneous motor starts, which could overload the backup source.


5 Power Quality Considerations

Modern galvanizing plants employ significant nonlinear loadsVFDs, induction heaters, and rectifier-based systemsthat generate harmonic currents. These can cause:

  • Overheating of neutral conductors and transformers.
  • Nuisance tripping of protective devices.
  • Interference with sensitive instrumentation and communication systems.
  • Reduction in motor and generator efficiency.
  • Resonance with power factor correction capacitors.

Mitigation Strategies


  • Conduct a harmonic study during detailed design, including worst-case operating scenarios.
  • Specify equipment with IEEE 519-compliant harmonic performance.
  • Install tuned harmonic filters or active harmonic conditioners as needed.
  • Use phase-shifting transformers to cancel specific harmonics (e.g., 12-pulse rectifier configurations).
  • Verify power factor correction capacitor banks are properly sized to avoid parallel resonance.
  • Consider the impact of VFD-induced common-mode voltages on motor bearing life in crane and conveyor applications.

Natural Gas Supply Systems

1 Determining Gas Demand

Many galvanizing furnaces select natural gas as the primary fuel for its efficiency, controllability, and lower emissions. The first step in system design is accurate demand characterization.

Heat Input Requirements

The furnace thermal demand comprises three components:

  1. Zinc melting load: The energy required to raise zinc from the charging temperature (typically 25150C, depending on whether ingots are preheated) to the operating bath temperature of 445465C, including the latent heat of fusion. Zinc has a melting point of 419.5C and a latent heat of fusion of approximately 112 kJ/kg. The sensible heat required to raise solid zinc from 25C to 419.5C is approximately 242 kJ/kg (using a mean specific heat of 0.39 kJ/(kgK)), and sensible heat to raise liquid zinc from 419.5C to 450C adds approximately 21 kJ/kg. The total theoretical energy to melt and superheat 1 kg of zinc is therefore approximately 375 kJ/kg (104 kWh/tonne). However, practical furnace efficiencies of 3560% mean that actual energy consumption ranges from 350700 kWh per tonne of zinc melted, depending on kettle design, insulation quality, and operating practice.

  2. Kettle steady-state losses: Heat losses through kettle walls, bath surface radiation, convection, and part immersion heating. These losses depend on kettle dimensions, refractory quality, and whether the kettle is externally heated or internally immersed.

  3. Kettle heat-up rate requirements: The maximum acceptable time from cold start to operating temperature drives the peak burner capacity. A typical specification allows 2448 hours for a cold-to-operating heat-up, which may require firing rates 1.52 times the steady-state demand.

Production-Linked Demand

$$\text{Peak Gas Demand} = \text{Furnace Steady-State Demand} + \text{Preheat/Furnace Additional Line Demand} + \text{Startup Contingency}$$

Worked Example

Consider a facility melting 4 tonnes of zinc per hour at steady state. Using a practical energy consumption of 500 kWh per tonne of zinc melted (mid-range of 350700 kWh/tonne), the melting load is:

$$\text{Melting Load} = 4 \text{ tonnes/hr} \times 500 \text{ kWh/tonne} = 2,000 \text{ kW} \approx 6.8 \text{ MMBtu/hr}$$

Assuming kettle steady-state losses of 30% of the melting load (a reasonable estimate for a well-insulated kettle), the total steady-state demand becomes approximately 2,600 kW (8.9 MMBtu/hr). For a 36-hour cold-start requirement, the startup firing rate may need to be 1.52 times the steady-state demand, resulting in a peak demand of 3,9005,200 kW (13.317.7 MMBtu/hr).

Gas Supply Pressure Requirements


  • Burner systems typically require supply pressures of 515 psig (35100 kPa) at the burner manifold.
  • The distribution system must be sized to maintain adequate pressure at the point of use during peak demand, accounting for pressure drops through piping, valves, and meters.
  • Facility gas pressure regulation trains should be designed with redundant regulators and adequate venting per NFPA 86.

2 Piping and Distribution System Design

Natural gas piping systems in galvanizing facilities must comply with ASME B31.1 (power piping) or ASME B31.3 (process piping) as applicable, as well as local codes. Key design considerations include:


  • Calculate pipe sizes based on allowable pressure drop and velocity limits (typically 6,00010,000 ft/min for high-pressure systems, lower for low-pressure systems).
  • Design with accessible isolation valves for maintenance without full-facility shutdown.
  • Include drip legs and sediment traps at low points to capture condensate and particulates.
  • Install flexible connections at furnace interfaces to accommodate thermal expansion and vibration.
  • Clearly identify all gas lines with proper labeling and signage.
  • Install gas detection systems in enclosed areas per NFPA 86 requirements.

3 Redundancy and Reliability Considerations

  • Design gas supply systems with dual entry points where possible to maintain supply if one line is being serviced.
  • Install automatic isolation valves that close on gas pressure loss to prevent uncontrolled gas release.
  • Coordinate with the gas utility on pipe sizing for future expansions, as upsizing the utility service later is costly and disruptive.
  • Ensure that dryer/preheater burners have independent gas supply drops with individual pressure regulation to prevent interaction with the main furnace gas system.

Process Water and Cooling Water Systems

1 Water Demand Assessment

Water systems in galvanizing facilities serve multiple purposes, each with distinct quality and flow requirements:

Process/Quench Water- Used for part quenching after galvanizing and for rinse stations.
- Quality requirements: Suspended solids <50 mg/L; pH 6.58.5; minimal oil/grease content.
- Flow varies with production rate; typical demand is 2080 L per tonne of parts processed.

Cooling Water- Cools furnace jackets (where water-cooled kettles are used), induction coil cooling, hydraulic systems, air compressor cooling, and various heat exchangers.
- Quality requirements: Total dissolved solids (TDS) <500 mg/L; suspended solids <10 mg/L; biological growth control; hardness controlled to prevent scaling.
- Temperature requirements typically 2535C supply, with acceptable return temperatures determined by equipment vendor specifications.

Cooling Tower Make-Up Water- Replaces evaporation and blow-down losses.
- The cooling tower make-up can be 25% of the recirculating flow, depending on evaporation rate and cycles of concentration.


2 Cooling Water System Design

Cooling water systems in galvanizing plants are commonly designed as closed-loop recirculating systems with cooling towers or chillers. The following design parameters require careful attention:

Temperature Control- Furnace and hydraulic systems typically require supply temperatures of 2535C.
- A well-designed cooling tower is capable of supplying water temperatures of 30C at design wet-bulb conditions.
- Chilled water systems are required only for specialized applications where close temperature control is mandated.

Flow and Pressure Requirements- Calculate total system flow based on heat rejection requirements, using:

$$\text{Heat Rejection} = \dot{m} \times c_p \times \Delta T$$

  • Where: = mass flow rate; cp = specific heat of water (approximately 4.18 kJ/(kgK)); T = temperature rise across the system.

Piping and Pumping- Design for a minimum velocity of 1.52.5 m/s to prevent settling and biological growth.
- Use corrosion-resistant materials; schedule 80 PVC or stainless steel for smaller lines, carbon steel with proper lining for larger mains.
- Install strainers and filters at critical equipment inlets to protect heat exchangers and pump seals.
- Provide redundant pumps (N+1 configuration) for critical cooling circuits.


3 Water Treatment and Quality Control

Water quality has a direct impact on equipment longevity and process stability:

  • Scaling: Hardness buildup in heat exchangers reduces efficiency; maintain hardness below 100 mg/L CaCO.
  • Corrosion: Dissolved oxygen and low pH can corrode piping and equipment; maintain pH in the range of 7.58.5.
  • Biological fouling: Open cooling towers are prone to algae and bacterial growth; implement a biocide program to maintain control.
  • Suspended solids: Carryover from the galvanizing process can lead to fouling of heat exchangers and downstream components; install filtration appropriately sized for solids load.

Design Recommendation: Incorporate a complete water treatment package into the initial designchemical feed systems, filtration, and monitoring instrumentationrather than retrofitting after operational problems emerge.


Compressed Air Systems

1 Demand Assessment

Compressed air in galvanizing plants serves various functions: pneumatic valve actuators, pneumatic cylinders in material handling, air knives for part drying, purging and cleaning operations, and instrumentation supply.

For demand calculations:

  • Estimate individual consumption of each pneumatic device, accounting for duty cycle (typically 550% for intermittent devices).
  • Total installed capacity must consider both average and peak flow, using:

$$\text{Total Demand} = \sum (\text{Individual Consumption} \times \text{Duty Cycle} \times \text{Simultaneity Factor})$$


  • The simultaneity factor (typically 0.70.9) reflects that not all devices operate at once.

2 Compressor Selection and Configuration

The selection of compressor type (reciprocating, rotary screw, centrifugal) depends on required capacity, duty, and air quality. For galvanizing plants, rotary screw compressors are commonly selected for their reliability and continuous-duty capability.

Sizing Criteria:
- Size the system for peak demand with a 20% margin to allow for:
- Future expansion.
- Normal degradation of performance over time.
- Inaccuracies in the demand estimate.
- Consider multiple smaller compressors rather than one large unit to permit part-load operation during low production periods and to provide partial redundancy.
- Specify variable speed drive (VSD) compressors to match output to demand and improve energy efficiency.


3 Air Drying and Filtration

Moisture in compressed air systems causes valve sticking, tool damage, and product quality problems. The installation of appropriately sized dryers and filters is essential.


  • Install filtration per ISO 8573-class requirements.
  • Locate dryers and filters downstream of the receiver tank with proper bypass for maintenance.
  • Provide adequate condensate drains at all low points and receiver tanks.

Integrated Utility Design: A Systems Approach

1 Interdependency Management

A galvanizing plant's utility systems are not isolated; they are deeply interconnected. Water-cooled furnace jackets depend on the integrity of the cooling water system; cooling towers depend on make-up water supply; compressed air systems require cooling water in many configurations. A systems approach considers these interdependencies explicitly:


  • Diversity of loads: Avoid placing all critical loads on a single utility bus or single water loop.
  • Fault isolation: Design sectionalizing valves and breakers so that a failure in one area does not disable the entire plant.
  • Instrumentation and alarms: Integrate utility monitoring into the facility's SCADA or control system to provide early warning of degraded performance.

2 Safety Margin Philosophy

Establish a consistent safety margin philosophy across all utilities:


  • 1015% for most systems to cover estimation uncertainties.
  • Up to 25% for furnace heating capacity where cold-start requirements dictate peak loading.
  • 3050% for backup generator capacity to cover both kettle heating and transient loads.
  • 20% for compressed air capacity to account for future production growth.

3 Future Expansion Allowance

Document the facility's business plan for production expansion and reflect it in utility sizing decisions. While building in full capacity for a 50% expansion immediately may be wasteful, structural allowancessuch as larger pipe sleeves, additional transformer space, and reserved breaker compartmentscan often be included in the initial design at modest cost.

Key strategies:


  • Install infrastructure (pipes, conduits, trays) sized for the largest anticipated future loads.
  • Make transformer substations expandable in design.
  • Locate chiller systems on the roof with capacity for additional units.
  • Plan for segregated harmonic filtering to accommodate additional VFD installations.

Design Review and Commissioning Best Practices

1 Design Review Process

Implement a structured design review process at the 30%, 60%, and 90% completion milestones. Each review should include:


  • Verification of load data against actual equipment selections.
  • Cross-checking of utility capacities against production schedules and process requirements.
  • Walk-down of the proposed layout to confirm equipment accessibility and maintenance clearance.
  • Review of failure modes and operational scenarios with experienced plant operators.

2 Commissioning Considerations

Commissioning is a critical phase where utility design assumptions are tested against reality:


  • Develop a clear startup sequence that avoids simultaneous high-inrush events.
  • Verify utility capacities under full-load conditions before bringing production online.
  • Test backup systems under simulated outage scenarios.
  • Document all actual operating conditions and compare against design data.
  • Provide comprehensive training to plant operators on utility system operation.

Conclusions and Recommendations

1 Key Takeaways

  1. Plan early: Engage utility providers 1824 months before commissioning; under-sizing and over-sizing are both costly, but in different ways.

  2. Base decisions on data: A detailed load inventory and demand profile analysis are the foundation of proper utility sizing.

  3. Design for resilience: Include backup power for critical loads (especially kettle heating), redundancy in water and gas systems, and quality mitigation for power and water.

  4. Integrate holistically: Utility systems must be designed together, not in isolation, to avoid hidden interdependency failures.

  5. Include expansion provisions: Consider future growth in utility capacity planning without over-investing in idle capacity.


2 Reference Standards and Compliance

Ensure that all utility designs comply with applicable national and local codes. The standards most relevant for hot-dip galvanizing facilities include:


3 Final Recommendations

For organizations planning a new galvanizing facility or a major expansion, we finalize with the following recommendations:

  • Invest in a professional energy study during the feasibility phase.
  • Conduct a harmonic study as part of the electrical design.
  • Engage an experienced galvanizing process engineer in utility planning discussions.
  • Prepare a comprehensive commissioning plan and verify all capacities before production startup.
  • Establish a continuous monitoring program for key utility parameters to facilitate predictive maintenance and identify emerging issues before they cause downtime.

The success of a hot-dip galvanizing plant depends as much on how well its utilities are planned as on the excellence of its process technology. A facility whose utility infrastructure is robust, appropriately sized, and designed for scalability will consistently outperform one where utilities were an afterthought. By applying the frameworks and methodologies outlined in this guide, engineering teams can deliver galvanizing facilities that set new standards for reliability, efficiency, and operational excellence.

Contact Us For Any Support Now
Table of Contents
GET IN TOUCH WITH Us
recommended articles
NEWS Cases
The 29th International Industrial Exhibition, METAL-EXPO 2023, Moscow, Russia.
Wedone Environment & Energy Technology (Shanghai) Co., Ltd. is present in Expo, Moscow.Mr. Leo Liu, the Sales Director of Wedone Technology is invited to give a technical presentation for “New Generation HDG Furnace – The Intelligent Digital Network Technology” at the XXIV International Seminar “Zinc for Corrosion Protection 2023” during the Expo.
Visit and Friendly Exchange with the Russian International Zinc Association Delegation
Wedone Group recently welcomed a delegation from the Russian International Zinc Association to our manufacturing facility for an on-site visit and technical exchange. The delegation was given a comprehensive tour of our production workshops, engineering facilities, and quality control processes, gaining firsthand insight into our manufacturing capabilities and technological strengths in the field of hot-dip galvanizing equipment.
Key Factors to Consider When Selecting Hot-Dip Galvanizing Equipment for Steel Structures and Tubes
Looking for a trusted Hot‑Dip Galvanizing Equipment Manufacturer? Read key criteria for selecting galvanizing gear for steel tubes, strut and structural steel production.
Wedone Technology Engages in Strategic Business Inspection to Vietnam
On May 10, 2026, the core team of Shanghai Wedone Environment & Energy Technology embarked on a strategic business inspection to Vietnam. This visit marks a crucial step in Wedone’s global strategy, aiming to deepen localized cooperation and expand its footprint in the Southeast Asian market.
A Promising Start for the Galvanizing Furnace Project in Turkey
TTM Endüstriyel is pleased to announce a strategic partnership with WEDONE Energy Technology to provide advanced engineering solutions for hot-dip galvanizing plants and equipment.This collaboration represents an important step toward expanding both companies’ capabilities in delivering high-quality industrial solutions to the global galvanizing industry.
Azerbaijan Clients Visit Wedone Technology for Advanced Equipment Consultation
On July 1, 2026, Shanghai Wedone Environment & Energy Technology welcomed a delegation of industry clients from Azerbaijan to its headquarters for an in-depth technical consultation and business meeting. The visit focused on advanced thermal equipment, high-efficiency production lines, and environmental energy solutions, marking another significant step forward in Wedone's expanding Eurasian business matrix.
12th Asia Pacific General Galvanizing Conference Exhibition, Yokogawa, Japan
Wedone Environment & Energy Technology (Shanghai) Co., Ltd. In present in APGGC 2023.
Strengthening Global Ties with the International Zinc Association
On September 24th of this year, Mr. Vladislav Polkin, the General Director of NCP "ZDC" from Russia, led a 20-member team to visit Wedone Environment & Energy Technology (Shanghai) Co., Ltd.. During this visit, Mr. Polkin and his team engaged in a warm and cordial exchange with our CEO, Mr. Lan Tian.
Wedone Technology and International Zinc Association Hold Friendly Talks at Changsha International Exhibition on Global Galvanizing Industry Import-Export Cooperation
On September 24, 2025, Wedone Environment & Energy Technology (Shanghai) Co., Ltd. participated in the Changsha International Exhibition. During the event, the company’s representatives met with Martin, President of the International Zinc Association, and held talks on the import and export of the international galvanizing industry.
From Blueprint to Production: What to Expect from a Turnkey Hot-Dip Galvanizing Plant Project
Learn the key stages of a turnkey hot-dip galvanizing plant project, from layout design and manufacturing to installation, commissioning and training.

cutting-edge galvanizing solutions

Our vision is to drive sustainable industrial progress by providing state-of-the-art technology, superior quality, and unmatched service.
Contact with us
Contact Person: LAN TIAN
Tel: +86 21 5835 6625
WhatsApp: +86 139 0195 1068
Company Address: 7th floor, Yinqiao Building, No. 58 Jinxin Road. Pudong District, Shanghai 201206, P.R. China
Customer service
detect